Main Stages of Works on the Restoration of the Church of the Transfiguration on Kizhi Island and their Fulfillment vs.Time. 1999-2014. The situation described as to the end of 2009.

Section I. Preliminary works (1999-2002)PoC'99'00'01'02'03'04'05'06'07'08'09'10'11'12'13'14
1. Development of conception of the Transfiguration Church restoration. Coordination and approval of the conception.100%
2. Development of the conception design of the conception design of the Church restoration. Coordination and approval of the conception design.100%
3. Development of the contractor design of a Complex Restoration, I-st stage100%
Section II. Preparatory period (2002-2008)PoC'99'00'01'02'03'04'05'06'07'08'09'10'11'12'13'14
1. Establishment of Restoration Service for preparatory period in the Kizhi Museum. Formation of the office.100%
2. Logging the 1st lot of special timber, transportation and warehousing on Kizhi island.100%
3. Logging the 2st lot of special timber, transportation and warehousing on Kizhi island.100%
4. Logging the 3rd lot of special timber, including boards for roofing, aspenwood for shingles, transportation and warehousing on Kizhi island.100%
5. Construction of special lifting equipment for raising the 1st (top) engineering tier. Test lifting of the top tier.100%
6. Construction of a restoration complex site in Vasilyevo village.100%
7. Restoration of Vitchurin's house and its adaptation for restorers' accommodation in Yamka village.100%
8. Working design and construction of the adjacent restoration-field around the church (ramp-platform and a temporary storage place).100%
9. Repair of m/s "Kizhi" and its adaptation for restorers' utility rooms.100%
10. Development of working documents for works of II-nd, III-d and IV-th stages of restoration.70%
11. Development of fire-fighting techniques for protection of Kizhi Pogost monuments.80%
12. Establishment of a restoration workshop for the Church iconostasis. Preparation of the premises in the houses of Pudozh Sector.100%
13. Construction of special lifting equipment for raising the III-VII-th engineering restoration tiers. Delivery of lots from Saint-Petersburg to Kizhi Island, warehousing.100%
14. Installation of the lifting equipment and suspension of the III-VII-th engineering restoration tiers. Installation of the transverse ferroconcrete foundations under the church framework for studs of the equipment for lifting and suspension of the engineering restoration tiers.100%
Section III. Main restoration works (2007-2014)PoC'99'00'01'02'03'04'05'06'07'08'09'10'11'12'13'14
1. Mastering the restoration complex. Acquisition, assembling and adjustment of wood-working equipment for restoration.100%
2. Trial restoration of the granary (XVIIIth century) from the village of Peldozhi, Pryazhinsky Districrt, in the restoration complex.100%
3. Restoration of original floor (XVIII, XIX centuries) of the Church of the Transfiguration.100%
4. Disassembly of the refectory. Transportation to the restoration complex. Restoration, fit-up. Assembly in the church log framework simultaneously with the VII and VI-th engineering restoration tiers.20%
5. Lifting church log framework (I-III-rd engineering restoration tiers) and suspension of the church log framework (IV-VII-th engineering restoration tiers) after the installation of the lifting system.90%
6. Restoration of the log framework successively from bottom to top with the VII-I engineering restoration tiers. Disassembly, transportation and restoration in the restoration complex, assembly on-site. VII-th engineering restoration tier1.0%
7. Reconstruction of the foundation of the Transfiguration Church.10%
8. Restoration of roofs of the Church of the Transfiguration.0%
9. Restoration of domes, "bochkas" and the porch of the Church of the Transfiguration.0%
10. Restoration of the carved gilded frame of the iconostasis.10%
11. Restoration of the iconostasis painting from the Church of the Transfiguration.60%
Section IV. Finishing stage. Project.PoC'99'00'01'02'03'04'05'06'07'08'09'10'11'12'13'14
1. Disassembly of the existent engineering reinforcement of the Church framework.0%
2. Construction and installation of the engineering reinforcement for the Church log framework2.0%
3. Restoration of the floor (XVIII and XIX cen.). Restoration of soleа and ambo.0%
4. Restoration of the church interior. Accommodation of the Church premises for conducting services.0%
5. Assembly of the iconostasis. Commissioning of the Church.0%

1↑ Note: time of restoration of the remaining engineering restoration tiers will become clear upon completion of restoration works on the VII-th engineering restoration

2↑ Note: works from this section are performed as needed; this issue will become clear after assembling restored church framework.